SOIL IN LABORATORY
Soil.
Q. 7 .
If in cut section the 20 cm. Material are okey but below in the soil has natural compaction of 90% and the contractor are asking for a payment are you going to pay ?
A. No
Q. 8.
How will you prepare monthly report ?
A. By summarizing the daily activities of the contractor .
Q. 9.
Supposing there are many activities going on that day , and same day request for next day activities was submitted by the contractor , what will be the flow of those request and when such request be acted ?
A . Distribute the request to fieldman and instruct them to finish first the previous request by doing overtime work if necessary , so that new request will be acted immediately the following day.
Q. 10.
If the contractor request to use salty water for concreting , is it possible to used such for concrete ?
A. If potable water is not available , salty water could be used for non-reinforced slab. To reinforced structure concrete must be dense and proper and strict supervision to be adopted . For pre-stressinh, salty water can not be used .
Q. 11.
What back slopes you would adopt in the rocky area and sandy area ?
A. Refer to typical section .
Q. 12.
How to monitor project progress ?
A. By plotting their monthly accomplishment in a bar chart.
Q. 13.
Steps taken in the preparation of a monthly certificate what deduction are usually applied ?
A. 1. Monthly payment for contractor
2. Monthly payment for consultant
3. Monthly residents engineers report
4. Monthly materials report
5. Following report which consists of ; a ) Beginning of project
b ) End of project
c ) Cost of project
d ) Percentage of progress
c ) percentage of delay
f ) Equipment list of contractor and his staff
g ) List of consultant
h ) Approval certificate for materials like steel and cement .