SOIL IN LABORATORY
Soil. Q. 7 . If in cut section the 20 cm. Material are okey but below in the soil has natural compaction of 90% and the contractor are asking for a payment are you going to pay ? A. No Q. 8. How will you prepare monthly report ? A. By summarizing the daily activities of the contractor . Q. 9. Supposing there are many activities going on that day , and same day request for next day activities was submitted by the contractor , what will be the flow of those request and when such request be acted ? A . Distribute the request to fieldman and instruct them to finish first the previous request by doing overtime work if necessary , so that new request will be acted immediately the following day. Q. 10. If the contractor request to use salty water for concreting , is it possible to used such for concrete ? A. If potable w...